F E E S A N D W O R K S T A G E S F O R
P R O J E C T M A N A G E M E N T F U L L S E R V I C E S
INITIAL CONSULTATIONS FOR ALL PROJECTS ARE FREE
OVERALL FEE PERCENTAGES
PROJECTS UP TO £75,000 CONTRACT VALUE BEFORE VAT – 9.5 %
PROJECTS OVER £75,000 CONTRACT VALUE BEFORE VAT – 7.5 %
WORK STAGE PERCENTAGES OF OVERALL FEE
STAGE A – FEASIBILITY APPRAISAL 5 % OF OVERALL FEE PERCENTAGE
STAGE B – FEASIBILITY BRIEF DEVELOPMENT 5 % OF OVERALL FEE PERCENTAGE
STAGE C – OUTLINE PROPOSALS 5 % OF OVERALL FEE PERCENTAGE
STAGE D – PLANNING APPLICATION 20 % OF OVERALL FEE PERCENTAGE
STAGE E – FINAL PROJECT DEVELOPMENT 10 % OF OVERALL FEE PERCENTAGE
STAGE F1 – BUILDING REGULATIONS 10 % OF OVERALL FEE PERCENTAGE
STAGE F2 – CONSTRUCTION INFORMATION 10 % OF OVERALL FEE PERCENTAGE
STAGE G – TENDER PREPARATION 10 % OF OVERALL FEE PERCENTAGE
STAGE H – TENDER ISSUE AND APPRAISAL 5 % OF OVERALL FEE PERCENTAGE
STAGE J – MOBILISATION OF BUILDER 5 % OF OVERALL FEE PERCENTAGE
STAGE K – SITE WORK TO COMPLETION 10 % OF OVERALL FEE PERCENTAGE
STAGE L – DEFECTS PERIOD 5 % OF OVERALL FEE PERCENTAGE
ALL FEES ARE CALCULATED ON THE COST OF BUILDING BEFORE ADDITION OF ANY V.A.T.